Buxton Beach Nourishment Update: Tuesday, July 14, 2026

DredgeWire15 Jul 2026Market
Automatically composed with AI from the cited sources

The dredge Liberty Island is now expected to arrive in Dare County during the week of July 27, 2026, a one-week delay caused by a specialized pump replacement in Norfolk, Virginia. A second dredge will arrive in mid-August to assist, maintaining the project’s scheduled completion by September 30, 2026. Approximately 2 million cubic yards of sand will be placed over an estimated 95-day construction period.