Corps, Port Freeport Mark Channel Milestone

The Waterways Journal31 Jul 2026Clients
Automatically composed with AI from the cited sources

The $295 million project, authorized by Congress in 2014 as a federal cost-shared project, has seen $209 million expended to date with federal funding reaching $207.8 million by 2023. Completed reaches include Reach 3 at 51 feet and Reach 4 at 26 feet; remaining dimensions include the Reach 1 Outer Bar at 58 feet, Jetty and Main Channel reaches at 56 feet, and Reach 2 at 51 feet. GLDD won the first dredging contract in September 2020, and Orion Group Holdings completed Reach 2 widening and bend-easing excavation contracts totaling $10.25 million by March 2023. Dredging finished in April, with contract completion scheduled for later in August and overall project completion in Q4 2026.

Context

This article supplies the project's cost structure ($295M total, $207.8M federal, $130M local) and contractor breakdown (GLDD, Orion) not carried in the July 28 ribbon-cutting reports.