DEME’s installation vessel Norse Wind has placed the first of 44 Vestas V236-15.0 MW turbines at the 660 MW Nordseecluster A, with the full set expected by end-2026 and commissioning planned for early 2027. The second phase, 900 MW Nordseecluster B, will add 60 turbines, with foundation installation beginning next year, turbine erection in 2028, and commercial operation in early 2029. The installation comes one week after DNV certified the third BSH milestone for Nordseecluster A, the regulatory step that authorised turbine installation.
The installation comes one week after DNV certified the third BSH milestone for Nordseecluster A, the regulatory step that authorised turbine installation.