The clearance campaign, running June–September 2026, involves disposal of three remaining UXOs using Low Order Deflagration, relocation of approximately 1,800 boulders, and removal of 12–15 out-of-service cables at the site 33 km off Suffolk. The 960 MW East Anglia Two project, developed by ScottishPower Renewables and awarded a CfD in AR6, will comprise 64 SG 14-236 DD turbines on monopile foundations supplied by Sif and Smulders; Cadeler will install foundations and turbines, Nexans will supply the export cable, and Hellenic Cables will provide inter-array cables to be installed by Seaway7.