The final concrete pour for the new container yard foundations took place on July 14, 2026, executed by the CareGo consortium of Dura Vermeer, GMB, and ABB with fiber-reinforced concrete across 115,000 square meters of AGV transfer areas. Construction had begun in May 2025, and the first phase of the expansion, which adds 51 hectares, 1,000 meters of deep-water berthing, and 31 stacking blocks to double terminal capacity, is targeted for completion by the end of 2026.