Installation of the remaining 75 turbines at the 1.2 GW Dogger Bank B is expected to continue until approximately the second quarter of 2027, with GE Vernova having switched marshalling for the wider 3.6 GW Dogger Bank Wind Farm from Able Seaton Port to Maraen Port of Nigg in May. The project, owned by SSE Renewables, Equinor, and Vårgrønn, completed foundation installation across all three phases in November 2025, and the first turbine at Dogger Bank B was installed in March 2026.