Court Denies GE Vernova Appeal in Vineyard Wind Case

OffshoreWIND.biz4 jun 2026Toelevering
Automatisch samengesteld met AI uit de vermelde bronnen

The project engineer appointed under the contract determined that GE Vernova owes Vineyard Wind more than USD 500 million in claims, leading Vineyard Wind to withhold around USD 308 million in payments stemming from a 2024 turbine blade failure. GE argued on appeal that the project reached its commercial operation date on 24 April and the Massachusetts Governor activated contracts on 27 April, so its exit would no longer cause irreparable harm; the judge rejected that, finding the project still depends on GE to reach full operational capacity.