The 28-metre-tall, 700-tonne transition pieces were supplied by CWHI and CFHI and marshalled at Forth Port's yard in Leith before installation by the heavy crane vessel Seaway Alfa Lift. The milestone follows the completion of all 54 monopiles at the site two months ago. Next in the sequence is the installation of 54 pin piles for 18 jacket foundations, with array cable and turbine installation campaigns to follow later this year.
The TP installation follows the July job openings and the project director's construction update earlier this week.