The project comprises 64 Vensys 5.7 MW turbines; first power was achieved in December 2025, and commissioning is expected later this year. Monopile supply was shared between GS Entec and Sif, with installation by Samhae ENC, Toseong Construction, and Hansan Maritime using the jack-up vessel Hansan 1. Export and inter-array cables were completed by Taihan Cable & Solution in July 2025. The wind farm holds a 20-year REC offtake agreement with Korea Southern Power (a KEPCO subsidiary) and a grid connection agreement from KEPCO.