Baltic Power offshore wind farm produces and delivers first electricity to Polish grid

DredgeWire15 Jul 2026Market
Automatically composed with AI from the cited sources

More than 50 of the 76 Vestas V236-15.0 MW turbines have been installed, and the first units have passed testing and supplied electricity to the national grid; grid operator PSE confirmed receipt at the onshore substation in Choczewo. All offshore export and inter-array cables are laid and buried, both offshore substations are installed and energised, and onshore infrastructure is complete, with the remaining turbine installations due by end‑2026 to reach the full 1.2 GW capacity.