Vestas Marks Installation of 100th V236-15.0 MW Turbine as Baltic Power Construction Progresses

OffshoreWIND.biz15 Jun 2026Supply chain
Automatically composed with AI from the cited sources

The 76th and final V236-15.0 MW turbine was installed at the Baltic Power site by Cadeler’s jack-up Wind Osprey, marking the 100th unit of that model installed at sea worldwide. First installation at the 1.2 GW Polish project occurred in July 2025; Van Oord completed monopile and transition piece installation in February–March 2026, while inter-array cabling continues. The joint venture between Orlen Group and Northland Power expects Baltic Power to become operational later this year.