JLR at risk of battery supply delays after Somerset factory turmoil

The Guardian20 jun 2026Toelevering
Automatisch samengesteld met AI uit de vermelde bronnen

Agratas has terminated main construction contractor Sir Robert McAlpine, replacing it with Tonroe Group Ltd, after more than two years of work under a temporary letter of limited authority during which SRM billed about £400m. The factory’s construction budget of £800m is expected to be exceeded by at least £500m, and the internal start-of-production date of January 2028 is already likely to slip; it is the second contractor exit after TClarke left in March. Equipment for a critical electricity substation has not been ordered, a ring road is not started, and senior manufacturing-engineering staff have departed.