CS Wind Offshore Delivers First Nordlicht I Transition Pieces

The 362-tonne transition pieces, first of 68 for the 980 MW Nordlicht I, departed CS Wind Offshore’s Aalborg facility for the site 85 km north of Borkum, where DEME will install them after placing the first monopile on 1 July. Vattenfall and former partner BASF awarded the monopile and TP contracts to EEW SPC and CS Wind Offshore in January 2025, and early production was reported ahead of schedule earlier this year. The full 1.6 GW Nordlicht cluster, comprising 112 Vestas V236-15.0 MW turbines, is scheduled for commissioning by 2029.