Inter-Array Cabling Completed at Nordseecluster A Offshore Wind Farm

OffshoreWIND.biz19 jun 2026Toelevering
Automatisch samengesteld met AI uit de vermelde bronnen

Forty-eight inter-array cables totalling approximately 185 km of 66 kV aluminium and copper conductor were laid, buried, terminated and tested by DeepOcean, using cable supplied by Hellenic Cables. The campaign connects the 44 Vestas 15 MW turbines to two offshore substations at the 660 MW site, where DEME installed the first turbine earlier this month. The cable completion follows that first turbine installation and keeps the project on track for full commissioning in early 2027.

Context

The cable completion follows that first turbine installation and keeps the project on track for full commissioning in early 2027.