Monday

Detached Vestas blade partially disrupts construction at major North Sea wind farm

During an analyst call, EnBW Deputy CEO and CFO Thomas Kustere said "certain activities have been temporarily paused as a precaution" — the company is not permitted to work on the affected turbine or on blades from the same production site. Kustere added that "the basic commissioning of the wind farm is progressing well and continues." EnBW also confirmed installation of the 64th and final turbine is imminent.
EnergyWatch